Mesa County South Broadway Shoulder Project Update
Project Update
Beginning Feb. 6 through Feb. 10, a full closure of Spoon Court will be in effect.
On Feb. 13, the project will undergo a winter shutdown through March. 20, 2023, due to the availability of asphalt.
Kindred Reserve parking will be open throughout the shutdown.
Project Schedule and Information
The project will resume operations on March 20, 2023, Monday through Friday, from 7 a.m. to 5 p.m. In the event weather conditions do not allow for work, the project may be periodically shut down for a short period until weather conditions improve.
Travel & Other Impacts
One-lane road operations will be in effect during construction hours for the majority of the duration of the project.
Stay informed
If you have any questions or concerns or want to be added to our public outreach contact list and receive construction updates, call or email us.